Progress
by end December 2002
In December the track plan (plotted out in Templot software by Richard Oldfield)
was finally delivered allowing us to finalise the location of the track and hence the
buildings on the modelled section. More building mock-ups in cardboard were built -
especially of the Hotel block as we got better town plans and some photos of the Central
Hotel. We also found a good photo of the goods depot. Flagstaff mountain was started from
expanded polystyrene sheet. Over Christmas Paul relaid the main lines and much of the yard
track according to the plans, but this is not shown in the photos below.